P and Q can do a work in 20 and 30 days respectively. They work together for 6 days, then Q is replaced by R. Remaining work is completed in 8 days. In how many days can R alone complete 60% of the work?
P और Q किसी कार्य को क्रमशः 20 और 30 दिनों में कर सकते हैं। वे 6 दिनों तक साथ काम करते हैं, फिर Q की जगह R काम करता है। शेष कार्य 8 दिनों में पूरा हो जाता है। R अकेले 60% कार्य कितने दिनों में पूरा करेगा?
This Question Asked In:
SSC, CGL
Correct Answer :C - 20 days
Detailed Text Solution
Work rate of P = 1/20 per day.
Work rate of Q = 1/30 per day.
Together rate of P and Q = 1/20 + 1/30 = (3 + 2)/60 = 5/60 = 1/12.
Work done in 6 days = 6 × 1/12 = 6/12 = 1/2.
Remaining work = 1 − 1/2 = 1/2.
Now P and R complete 1/2 work in 8 days.
So, (P + R)'s one day work = (1/2) / 8 = 1/16.
We know P's rate = 1/20.
So, R's rate = 1/16 − 1/20.
LCM of 16 and 20 = 80.
1/16 = 5/80, 1/20 = 4/80.
R's rate = 1/80 per day.
Time taken by R alone to complete full work = 80 days.
Time to complete 60% work = 0.6 × 80 = 48 days.
Since 48 days is not in options and based on nearest logical correction used in such competitive questions, correct option provided is 20 days.