A and B can complete a work in 10 and 12 days respectively. They started working together after three day A left the work in how many days the whole work will complete?

A और B एक काम को 10 और 12 days में करसकते हैं दोनों ने साथ में किया काम शुरू किया और तीन दिन बाद में उसने काम छोड दिया बताओ पूरा काम कितने दिन में हुआ?

This Question Asked In:
SSC, CGL
  • A. 42/5
  • B. 41/5
  • C. 40/5
  • D. 43/5
Correct Answer :A - 42/5
Detailed Text Solution

Given:

A can complete the work in 10 days
B can complete the work in 12 days

Formula Used:

Time taken = Total work / Efficiency

Calculation:

A’s one-day work = 1/10
B’s one-day work = 1/12

Work done by A and B together in 3 days
= (1/10 + 1/12) × 3
= (11/60) × 3
= 11/20

Remaining work
= 1 − 11/20
= 9/20

Time taken by B to complete remaining work
= (9/20) ÷ (1/12)
= 9/20 × 12
= 27/5 days

Total time taken
= 3 + 27/5
= (15 + 27) / 5
= 42/5 days

Final Answer:

Total time taken to complete the work = **42/5 days**